Entomology Hall Renovations
| 23 April 2009 The air handler pad was poured in the attic and took 7 yards of concrete with 90 gallons of vibration dampening mixture. Dry wall construction will begin next week. Because of Fire Marshal concerns about hall width, a chase will not be built around piping in the stairwell. Forest Service likely move date is March 2010. - Gary Brewer |