Entomology Hall Renovations - 2/12/09

Framing is well underway and estimated to be about half completed.

The work on the first floor conference room and into the stairwell is to install a water condensate line extending from the third floor to the sub-basement. The false alarm earlier this week was caused by someone bumping into a part of the existing fire alarm. We will be notified if this happens again.

The third floor construction remains on target for an August finish. Work on the first floor lab may start in May.