Entomology Hall Renovations

Work is on mostly on schedule; some aspects are ahead, plumbing is slightly behind schedule.

Dry wall work is completed.

Casework has been delivered and is being stored on the third floor (see pictures).

Delivery of the fume hoods is behind schedule but installation should begin on 15 June.

Work on the first floor lab is beginning this week.

Scheduled outages include power on Saturday June 13 (7 AM to 4:30 PM) and water on Saturday June 20 (7 AM to 12 noon).

- Gary Brewer

cabinets stored upstairs

Cabinets stored in room 311
cabinets installed

Cabinets installed in room 310
finished walls in room 309

Finished walls in room 309